Project Budget: $44,000.00 + GST
Project Timeline: 2 weeks
Scope of works:
Supply and install the following:
- Suspended ceilings at 7500 mm hight
- Build and install partition walls to cover existing concrete external wall
- Supply all lift access
- Painting all walls and ceilings