Interior Fitout
Project Budget: $32,000.00 + GST
Project Timeline: 4 Weeks
Scope of works:
Supply and install the following:
- Demolition of existing bathroom
- removal all carpets and existing joinery / cabinets
- Asbestos removal
- Build new partition walls
- install new door jamb / new doors
- Patch and repair all ceilings
- Identify sound leakages and soundproof all affected alls
- All internal painting
- Ceilings, walls, skirtings, doors
- Paint common areas stairway
- Install industrial gym rubber floor mats